06 February 2018

Pre-Shipment Report(PSI) for the 20 ml glass bottle product manufactured in Guangzhou

This is the summary of the full report of the Pre-Shipment  Inspection Report(PSI) of the  20ML glass bottle on December 1,2017 at Guangzhou City, China.

According to our inspection standard ISO2859, workmanship fail because of several reasons. Product quantity, product  description/style/color, on-site tests, packaging and shipping mark are all pending. Below are the details of why it’s pending.

Workmanship -FAIL, Beyond AQL:

The following  are the minor problems found on the 10  items with 35pcs as corresponding  sample size  of each total of 315  sampling size.

– scratch mark on unit surface

– bubble mark  inside the unit body

– poor silk screen of unit word

– oil mark  inside the unit body

– dirty mark on export  carton

– dent mark on unit’s lid surface

*As for the order quantity  of 16,200 pieces 4.0 were minor,21 were accepted ,22 were rejected and 34 found.

*As for the inspection level 2.5 major, found 5, 14 were accepted and 15 rejected.

* 1 rejected from sampling plan.

Product Quantity- Pending

Actual quantity of glass bottle was 16,365 instead of 16,200 which was stated on PI.

Product Description/Style/Color-Pending

All glass bottles were finished and packed into carton but all cartons were not sealed by tape. The factory claimed that they would seal before shipping.

All covers were not assembled during this inspection and the cover components were not enough.

Actual part quantity details below;

cover component name:                        actual quantity:

lid                                                   2 cartons, total of 11,972 pcs.

gasket                                                 1,700 pieces

dropper                                              1,700 pieces

rubber head                                       1 bag total of 500 pcs.

All the lid found no line at the bottom which was required on the specifications.

The shape of the rubber head in all items were found different from specifications on PDF file.

(For  further details ,you may check the photos.)

On-site Test- Pending

The capacity of the bottle was not in the specification requirements. Details refer to Product Measurement Check.

The factory did not allow us to conduct carton drop test during the inspection.(Details refer to photos.)

Packaging- Pending

All glass bottles were finished and packed into carton but all cartons  were not sealed by tape however the factory ensured us that they will seal the cartons before shipping.

Shipping Mark-Pending

All items has no shipping mark found on the export cartons. (Please refer to photos for further details.)

For further information on the whole PSI process, please see below:

What is a Pre-Shipment Inspection Report(PSI)

Before shipping out, our team initiates a Pre-shipment Inspection Report with your Chinese supplier. This service is available either at the vendor’s office or in factory. This is done to ensure that your products fully conform to the agreed specs and there is no dispute over the details of your order.

What do we look for during PSI?

We carefully inspect according to the following criteria:

1.Product quantity

2.Packing

3.Product conformity

4.Workmanship appearance/function tests

5.Reliability/ function tests

6.Measurements

7.Our inspection is supported by clear photos to show the finest details of our work, we photograph, the packing, appearance, any defects, bad workmanship, etc.

We clearly photograph the measurements as well as the function tests for example, done by stacking weights, etc…